Fremont Connector Project

In late 2021, Port Coquitlam and Coquitlam completed the preliminary design and alignment for the future Fremont Connector (PDF), the 3.5-kilometre arterial road extension that will link north Port Coquitlam with northeast Coquitlam. 

Detailed design of the project is expected to begin later in 2024, with construction anticipated to begin in the next few years.

Project Background 

The two cities have been working closely together to plan the important route, which will meet current and future transportation needs in both communities.

While the Fremont Connector has been identified in the Official Community Plans and transportation plans of both cities for many years, the new need for the route continues to grow as more homes and development come to the area. 

The project will bring:

  • Important road and active transportation improvements to support Metro Vancouver’s northeast sector;
  • Improved access for residents and businesses; and
  • Reduced traffic in other areas of the road network, including Coast Meridian Road, Prairie Avenue and Cedar Drive.

Preliminary Design Details

The preliminary design for Fremont Connector consists of two travel lanes, intersection improvements and an adjacent multi-use pathway for pedestrians and cyclists. 

The preliminary alignment: 

  • Follows the existing Fremont Street road allowance from the east end of Victoria Drive south to Lincoln Avenue;
  • Continues south from Lincoln Avenue along the existing road alignments for Devon Road, Prairie Avenue and Burns Road; and
  • Joins the completed southern section of the Fremont Connector, which links to Lougheed Highway and the Mary Hill Bypass.  

Next Steps and Estimated Timelines

  • Engineering Detailed Design: 2024-2026
  • Public Information Sharing: 2024-2025
  • Preloading: 2026-2027
  • Construction Start: 2027

Project details and timelines may change. Watch this webpage for updates as the project progresses. 

Stay Informed

To stay informed by the City about the Pipeline Road Upgrade Project, monitor this page visit or sign up for Fremont Connector updates or follow the City’s social media channels, including Facebook and Twitter and Instagram for news and information.